Estimating guide
Will the supplier quote still hold after bid day?
A window supplier can give you a figure for Friday’s bid and still need to re-quote before you can place the order. Check when the quote expires, what starts the lead time and when the crew needs the material on site.
Jump to the six-window exampleRead the quote against the job calendar
Put the supplier’s deadline beside the first day your team can meet it. Does the supplier need to receive a purchase order, accept it, or receive a deposit? Copy the condition from the quote. If the contractor expects an award on Friday but the quote requires an accepted order by Thursday, flag the gap before issuing the bid.
Then work back from the day the crew needs the material. Check whether the quoted lead time ends at dispatch or delivery, whether it uses working or calendar days, and what starts the clock. An accepted order can still be waiting on field dimensions, finish approval or released shop drawings.
If a date or condition is missing, record the question and who will get the supplier’s answer. Use the bid-leveling checklist first if you are still deciding which quote covers the work.
Six windows needed on April 16
This fictional remodel uses calendar days throughout. Window schedule A-6, revision 2, calls for six identical casements, W1 through W6. The estimator carries six each in the takeoff. The crew needs all six delivered to the jobsite by April 16.
- March 5 · Bid due
- Supplier quote Q-17A covers the six units. It requires the supplier to accept the purchase order by March 12. The contractor expects to have authority to place the order on March 19. The quote expires seven days before the earliest planned order.
- March 22 · Expected drawing approval
- Q-17A allows 21 days to dispatch, starting at the later of order acceptance or drawing approval. Assume acceptance on March 19 and approval on March 22. With a written extension covering acceptance, dispatch would fall on April 12. Three days in transit puts delivery on April 15, one day before the crew needs the windows.
- March 18 · Revised quote received
- Q-17B covers the same six units and holds its terms for orders the supplier accepts through March 26. It now allows 28 days from the same starting event to dispatch. March 22 plus 28 days gives April 19. Add three days in transit and the projected delivery moves to April 22, six days after the crew needs the units.
The second quote closes the order-date gap and opens a delivery gap. Keep the count at six. Have the project lead check whether the crew can use an April 22 delivery or the supplier can confirm an earlier one. Until someone resolves that question, carry April 16 as an open job requirement.
What goes in the proposal and the purchasing handoff?
On March 5, the estimator knows that Q-17A expires before the expected order. Ask for written terms covering the later order. If the answer is still pending when the bid is due, have the bid reviewer decide whether to qualify the offer under the project’s instructions or hold it. A line the client can act on is “For a March 19 order, we need the supplier to reconfirm the window pricing and the April 16 delivery date.”
On March 18, keep the issued proposal with Q-17A as its original basis. Attach Q-17B to the working estimate. Compare the specification, quantity, freight, delivery point and commercial terms as well as the new lead time. If the review changes what you can offer the client, identify the affected scope and timing in a dated proposal revision.
A handoff the buyer can use
Window package · A-6 rev 2 · W1–W6, six each. Q-17B requires order acceptance by March 26. Drawing approval expected March 22. Projected jobsite delivery April 22 against April 16 required. Hold order. Project lead to review the six-day gap with the superintendent and return a decision to purchasing before March 19.
When the decision comes back, enter who authorized the next step and when. After placing an authorized order, reconcile the supplier’s acknowledgment against the reviewed quote, approved drawings and delivery location. Replace projected dates with confirmed dates as each becomes available.
Try the same revision in an estimating demo
Give the estimator Q-17A and keep Q-17B for a second pass. Ask a colleague who missed the demo to open the records and answer three questions.
- Which drawing and quote supported the six units in the bid the client actually received?
- Can the colleague find the revised delivery calculation, the six-day gap and the person assigned to resolve it?
- If drawing approval slips another two calendar days, can they show April 24 as the new projected delivery while preserving both the issued offer and the April 16 site requirement?
A spreadsheet and a saved quote can serve as the comparison. Mark which steps the software supports and which require the estimator or buyer to keep a separate record.